In the Amur region it will be the first road of the second technical category.
Within the framework of the project of a transboundary bridge over the Amur, a two-lane highway with congresses and adjacencies is being built. The length of the road is about 15 kilometers. With the beginning of the road-building season, contractors began to lay asphalt concrete pavement.
As the chief engineer of Asphalt JSC, Vyacheslav Kudryavtsev, said, this would be a motorway of the second technical category, there are no more such roads in the region. “At this facility, the capital type of coverage, that is, reinforcement of clothing layers is envisaged. Here, road pavement is designed for all types of traffic loads of all categories of road transport, ”explained Vyacheslav Kudryavtsev.
Delivery of the object is scheduled for December, but to finish all the work that are associated with the summer period, to be mid-autumn. “Since we had a long spring, cold, now we are fully on the pace to pass all the time,” – concluded the chief engineer of JSC “Asphalt”.